Khusnullin promised to restore the second railway track of the Crimean bridge in six months

Khusnullin promised to restore the second railway track of the Crimean bridge in six months

[ad_1]

Deputy Prime Minister Marat Khusnullin, who heads the government commission to eliminate the consequences of damage to the Crimean bridge, said that the restoration of the second track on the railway part of the bridge would be completed in 6-7 months. Former government instructed restore the railway track by the winter of 2023.

Restoration work leads Nizhneangarsktransstroy.

“We are his (second way.— “b”) within 6-7 months we will restore in such a working mode, ”Mr. Khusnullin told reporters, noting that the project for restoration work is almost ready (quote from “RIA News”). Now the movement is carried out in reverse mode on one way.

Restoration work on the railway track of the Crimean bridge started October 8th.

First span of the first span of the road part of the bridge Was installed November 8th. Works on the installation of the second span have been completed November 12th. In total, four spans need to be restored.

Former Deputy Prime Minister promised to restore traffic on both lanes of the part of the bridge destroyed during the explosion by December 20 (from December 5 – one lane each).

On October 8, on the Krymsky bridge, as a result of a truck explosion, a partial collapse of automobile spans occurred. A train with fuel tanks caught fire on the railway part of the bridge.

Maria Fedotova