The Ministry of Defense refused a penalty for violating the delivery deadlines for the radar – Kommersant

The Ministry of Defense refused a penalty for violating the delivery deadlines for the radar - Kommersant

[ad_1]

Moscow Arbitration Court refused to recover from the Nizhny Novgorod Research Institute of Radio Engineering a penalty in the amount of 38.4 million rubles. in favor of the Ministry of Defense of the Russian Federation. In 2019, NNIIRT undertook to manufacture and supply the modernized 59N6-T radar station to the troops, but did not meet the deadline.

The 59N6-T mobile three-dimensional radar can also detect hypersonic missiles. It is automatically capable of tracking targets flying at speeds of up to 8 thousand km/h at a range of up to 450 km and an altitude of up to 200 km, including in jamming conditions. Installation cost – 600 million rubles.

The manufacturing institute was supposed to deliver the station by the end of 2021, but the delivery was nine months late, and the military charged him a penalty for this. However, the court referred to the anti-crisis moratorium introduced by the Russian government and valid from April to October 2022. As an “instrument of state regulation of the economy,” the moratorium is aimed at minimizing the consequences of the sanctions regime, the court indicated, and the overdue state defense order of NNIIRT also fell under the scope of this moratorium.

Ivan Sergeev, Nizhny Novgorod