JSC Russian Railways is laying a new track next to a flood-damaged branch at BAM
[ad_1]
JSC Russian Railways began laying a new track on the BAM at the Nizhneangarsk-Kholodnaya section, where on August 19, due to the destruction of the dam and the exit from the Kholodnaya River, about 1 thousand meters of embankment were washed out, and the movement of trains along the highway completely stopped. How informs The press service of the company, specialists began to form an embankment for a new path “without waiting for the water to subside completely.”
“In total, it will be necessary to restore 1,800 meters of a railway track, a bridge crossing, 1,200 meters of a contact network and 20 contact poles. The main forces are now sent to help the regional authorities in eliminating the breakthrough of the protective dam and returning the Kholodnaya River to its channel, ”the message says.
About 200 people and about 50 pieces of equipment are now working at the site of the washout at BAM – dump trucks, bulldozers, and a grader.